Line 5

July 2013 update

Kiln 1st pier heat shields were positioned
Kiln main burner pipe under refractory laying
Precalciner down comer duct installation in progress
Pre heater upto 1st cyclone outlet gas duct manifold in position
Down comer duct support at Rawmill end
Down comer duct foundation ready for structural installation
Cooler Booster fan is being insulated
Kiln hood being insulated
TAD Brick lining in good progress using kiln arch machine
Raw meal silo aeration blowers with connected pipe lines
Level-66 air slides are in place with required platforms
Level-40.5 new platform between silos 1 & 2 being paved
Coal mill top level- 30 screw conveyor drive ready
Coal mill Girth gear pinion assembly- Ready for installation- Alignment to start from 25th July
Schenck – HCV – IBAU pump system Compressor and Cooler are in position
AC-200 Gallery structure – ready for buckets insertion
Cleared from all old set clinker under belt conveyor – at silo top.
Cyclone-4 slope part being paved with castable