Line 5

Jan 2014 update

Preheater fan motor start_up

Raw Mill 1 Fan start up in cold weather

Raw Mill 2 Run

Coal Mill Test

Pyro process ready for operation
Coal mill ready for operation with media charged
Pump house – ready for operation with cooling water supply system
RM-1 final gas ducts installation in progress with target to run the mill by 3rd wk. Feb-2014

RM-2 is already producing the raw meal and filling the silos.