Line 5

August 2013 update

A view of Coal firing system- Kiln and cooler building
Pre heater compressor pipe line on insulated condition
Kiln hood and cooler refractory lining completed
Raw meal silo multi cyclones casings are being insulated
Kiln feed system bag filter been insulated
Pre heater down comer duct joining to ID fan inlet
Pre heater outlet duct joint with top cyclones
Pre heater down comer duct –Twin duct joining at level -48 meter
Kiln feed system and coal firing system blower’s bank ready
Coal mill main drive motor foundation completed
Kiln ID fan with connected gas duct in position
Level-78 platform is ready
Kiln feed weigh feeders are in position
Raw meal silos chutes from level60 to 40 are in position
Raw mill main bag filter casing insulation was initiated
Pre heater fan and connected duct in position
Coal mill- top dust plant in 75% completed
Schenck main burner firing system is ready
Water system pipes are ready with loop arrangement.
Clinker silo top Pivot conveyor being installed

August 2013 update

Cable Pulling at TP17 (Kiln Inlet)
Cable termination at Cooler MCC Panel in TP7
Cooler Fans Variable Speed Drives Controller cabling
Fiber Optic cablings and setting up of DCS Server panel
Installation of New Work-station for Line 5 DCS
Basic Graphic and control software of Raw Mill loaded to system
Pre Commissioning of Cooler Hydraulic System