Line 31 December 2012 update

Internal kiln shell welding at joint 4 in progress
Temporary shield (plastic wrapped) for temperature control inside kiln to permit welding works with maintained temperature
Kiln outlet CowShell pre-assembly completed and ready for lifting
All 7 joints barricade with special enclosure to enable internal welding works done in winter (ambient not lower than 20 degrees centigrade)
Kiln girth gear lifting in progress
Kiln girth gear in position (yet to be aligned)
4th Cyclone in postion and work in progress
4th Cyclone Side View
Pre Calciner 48th Meter level support erection in progress
Pre-calciner to 53 meter level & 3rd Cyclone erection progressing
Cooler Side Casing Installation in progress
Internal view on progress of side casing installation
Cooler Fan installation in progress
Heat Exchanger Inlet & Outlet duct erection in progress
Gas Duct support erection on progress
RM1 Clay apron feeder completed installation
RM1 Limestone feeder completed installation
Silo -1 impact cone installed inside the silo
RM-2, left side bank casing was positioned- Welding to be initiated
Kiln Feed Bucket Elevator & Struture foundation ready for concrete pour
Jaw crusher eccentric shaft been dismantled for NDT check


Completed Steel base frame and floor closing at TP 17
MCC & RPC Panels moved to site at TP7

TP7 MCC assembly works in progress
TP7 Kiln oulet in-commer panel in position